☰ Menu
AZ-900 · 21/473
← Prev Next →

Topic 1 · Question 21

Note: The question is included in a number of questions that depicts the identical set-up. However, every question has a distinctive result. Establish if the solution satisfies the requirements.
You are tasked with deploying a critical LOB application, which will be installed on a virtual machine, to Azure.
You are informed that the application deployment strategy should allow for a guaranteed availability of 99.99 percent. You need to make sure that the strategy requires as little virtual machines and availability zones as possible.
Solution: You include two virtual machines and two availability zones in your strategy.
Does the solution meet the goal?

A. Yes

B. No